On 19/07/2017 at 7:41 PM, Santa07 said:

Looks like there's only a few weeks left of coaster construction, which is great since that'll mean they have plenty of time to work on theming and getting the ride tested before opening.

 

On 19/07/2017 at 7:50 PM, themagician said:

I'm thinking the lift hill could take a week or two to construct, but I imagine all track will be installed within the next 2-3 weeks. Train arrives early to mid August, testing begins by the end of August to early September.

I say the lift hill and drop will be completed by Saturday 12th August 2017...

temp.png.818bdcfe4e910dbf6819ea8157491168.png

Here's my pointless update for this weekend. (Honestly though, the coverage this week has been amazing and extensive!)

However, not everything has been covered! Which means there is actually something to mention :o

Grouting of the supports has started around the Incline Dive Loop and the work on the Non-Inverted Loop seems to be torquing - definitely sounds like it.

As I was in somewhat of a rush, here are my moving-car shots for the weekend of the 22nd and 23rd of July.

Comparison Shot 1

DSCN8145.thumb.JPG.243c008b7aa23dfc08e1214977f5aa2c.JPG

Okay so I lied, the car was stationary for the taking of this picture.

Not Comparison Shot 1

DSCN8151.thumb.JPG.178cb2dfab5a1f110b3608a7f13e582a.JPG

Driving alongside all of this is going to be awesome. Imagine racing the train along the bunny hills. you can do it in roughly two months. (Hopefully, all the construction fences are gone once testing starts)

DSCN8147.thumb.JPG.a8ab79c329353adf45196bf1934218d4.JPG

The incline on the lift hill is going to be terrifying... for most guests.

DSCN8149.thumb.JPG.c08425924c293b1a2ecc8c91f2929388.JPG

Warner Bros. Movie World wins the Australian Parkz Skyline Award

Construction Fence wins Parkz Most Hated Photographic Obstruction 'Award'

DSCN8150.thumb.JPG.0249b759f273aeec9a4820bd3c02d08a.JPG

There are only three main lift hill supports. and two of them are *partially* complete.

DSCN8149.thumb.JPG.c08425924c293b1a2ecc8c91f2929388.JPG

The lift hill track reaches the height requirement for almost every kids ride on the Gold Coast.

@themagician did you get the chance to take pictures of the track after the helix? We don't have any pictures of that part yet. Awesome pics! 

9 minutes ago, LORD_Noodle said:

@themagician is that the last support to go up for the entire track?

No, there is plenty more track to be installed. The supports installed today just reach the height of GL at 33 meters, that means there's about another 25-30 metres of supports to go up on the one they were working on today.

 

On 24/07/2017 at 4:47 PM, themagician said:

IMG_0151.thumb.JPG.18172b5d7d09a7116bde86e822938223.JPG

IMG_0160.thumb.JPG.6cd9a7abbd421742375f218a13891dbf.JPG

You can see all the supports that need to be installed above.

Train is no longer in the compound. 

38 minutes ago, LORD_Noodle said:

Will they have 2 trains going simultaneously?

train 1 will depart as train 2 hangs in the break run for a moment. 

There will be a trim brake (probably magnetic) to bring the speed down, followed by a block brake (mechanical) which is capable of actually stopping the train. Once a train enters this block brake, the chain lift will be declared empty and allow for the train in station to depart.

Once the station train has departed, it marks the station block as empty and the block brakes release the train to roll around into the station. The station is now occupied, the chain lift is occupied but the block brake is empty. Only in these conditions will the chain lift take the train entirely to the top and allow it to crest the hill. Once this train reaches that block brake again, the chain lift is then declared empty again and the cycle goes on...

Thats what I was thinking @Skeeta, however if the second train hasn't arrived yet, that might be the one they will have on display for assembly and for use for the advert. Or they are waiting on the other parts of the train to arrive, and for now they've closed the container shut.

I thought the exact same thing when the train arrived and was promptly hauled off the compound. It's gotta be the second train that will get assembled in the maintenance bay. Greg did also mention that the train will be sitting in the compound to film the TVC too.

Guest
This topic is now closed to further replies.

Recently Browsing 0

  • No registered users viewing this page.

Important Information

By using this site, you agree to our Terms of Use. We have placed cookies on your device to help make this website better. You can adjust your cookie settings, otherwise we'll assume you're okay to continue.

Configure browser push notifications

Chrome (Android)
  1. Tap the lock icon next to the address bar.
  2. Tap Permissions → Notifications.
  3. Adjust your preference.
Chrome (Desktop)
  1. Click the padlock icon in the address bar.
  2. Select Site settings.
  3. Find Notifications and adjust your preference.