Mid-week Update courtesy of an unplanned visit. [28-06-17]
Storage Lot
The smallest support in the lift hill area. (Literally the only reason I've included this photo - it's a cute little thing compared to the behemoth its underneath)
Whatever these things are. (Yeah yeah.. I recognise that it's scaffolding.)
Brake run catwalks.
There are three new pieces in the lot (since my previous update) - however, due to the position of the sun I have no good photos of them.
Station/Brake Run/Lift Hill
Catwalk installation preparation
Non-Inverted Loop
The shot that you're going to see a lot throughout the rides lifetime. (Well, minus the fencing... and probably from a different angle... oh and maybe a visible train... but that's basically still the same, right?)
More supports for the first airtime hill. Look to be fully assembled and will likely be slotted in place fully completed.
Remember the thumbnail for that Parkz Update? Yeah, there's track there now. Swooping down into the loop is going to be amazing.
This shot... I like this shot
I also like this shot. I like this shot very much.