Not in Qld they don’t, which is what is relevant here.
you can find all requirements for the commission of new rides on the below link, zero mention of minimum testing hours, only that they meet manufacturer standards
https://www.worksafe.qld.gov.au/__data/assets/pdf_file/0016/118501/amusement-devices-cop-2023.pdf
There is also people online who say they work for Mack and typical rides only require 100-150 cycles. So there is nothing definitive as Mack don’t publish their requirements publicly.
JR has already done a test cycle, so I am not sure how that is applied in this case. The coaster weaves around the land so a large proponent of the theming land-wise is outside the envelop aside from the temple area, so that work can continue whilst commissioning begins